Labor Planning Homepage

See where a job stands against its baseline forecast, actuals and projected hours, then edit or re-forecast it, all in one place.

 Note: Some tutorials in this article are interactive. Click the blinking target to advance to the next step.

Contents

Navigation

Productivity Risks

Baseline/Scheduled/Actual Hours

View Impact

Labor Need

Version History

Key Metrics Bar

Forecast Variance

Labor Loading Graph

Hours/Workers (Max)/Workers (Avg)

Edit Forecast

Re-forecast a Job

Save Draft and Publish

Jobs That Haven't Started

Planned Overmanning

Recommended Supervisors

Labor Consumption Graph

Slippage

Progress To Completion and Current Budget

Labor Plan Analysis Table

 

Related Material

Schedule To Your Forecast

Forecast Builder

Labor Recommendation Modal

Labor Request Baseball Card

Role Ratios

Role Categories


Navigation

 

  • Click the name of a job to access the Baseball Card.
  • Click on the image-png Icon to access the job's Pages
  • Navigate to the Labor Planning Homepage

↑ Back to top


Productivity Risks

 

  • The Productivity Risks Banner appears at the top of the page when a job shows signs of a potential labor hours overrun.

  • Click to expand the Productivity Risks Panel on the right.
  • More Information about Productivity Risks

↑ Back to top


Baseline/Scheduled/Actual Hours

  • Click each chip to show or hide that series on the Labor Loading and Labor Consumption graphs. Scheduled Workers is off by default.
  • The Baseline Forecast is represented by a grey color mountain range shape
  • The Scheduled Workers are represented by dark blue bars on the chart
  • The Actual Hours are represented by an orange line across dates on the chart
  • The Data Date is the last date RIVET received information regarding the actual hours on a job. The Data Date and Today markers appear as vertical lines on both graphs.
  • Turning off Baseline Forecast shows the current published forecast for past weeks (when no actuals are available), and Slippage compares to the current published forecast instead. 

↑ Back to top


View Impact

  • The View Impact Modal will compare the baseline forecast to your actual hours plus current published forecast.
  • The impact is shown by hours as well as number of workers and recommended supervisors on the job
  • The Impact Report is exportable as a PDF

↑ Back to top


Labor Need

  • RIVET will provide Role Recommendations to level the scheduled labor with the job's forecast.
  • These Role Recommendations are editable by you.
  • More Information

↑ Back to top


Version History

  • Clicking on Version History will show you every previously published version of the job's forecast. 
  • You can select which version of the forecast is the "baseline" by hovering over that version and clicking the Frame 3180  icon
  • Click the ⋮ menu on any version to View it, see its Info, Restore this Version, or Edit it.
↑ Back to top

Key Metrics Bar

  • The Key Metrics Bar summarizes the job’s hours, budget, and labor rates, along with how the current forecast compares to the job’s projection or budget.
  • Clicking on a metric will show more information on the value and how it's calculated.  
  • If a metric can't be calculated because the job is missing data, the box will tell you which data to add to the job so you can see the metric.

↑ Back to top


Forecast Variance

  • Forecast Variance is the difference between the Current Forecasted Hours at Completion and the job’s Projected Hours at Completion (or Current Hours Budget if there’s no projection). Click the number to see the math.
  • Click Re-forecast to switch into Edit Forecast mode and open the Re-forecast panel. RIVET automatically builds a draft forecast that lands on your projection, which you can review before saving or publishing. See Re-forecast a Job for more information. 

↑ Back to top



Labor Loading Graph

  • The Labor Loading Graph shows workers per week for the baseline forecast, the current published forecast, actual hours, and scheduled workers (if enabled). The Baseline Peak line marks the baseline’s highest crew size.
  • Click Edit Forecast to open the forecast grid above the graph, lined up week by week with both graphs.
  • In Edit Forecast mode, use the Forecast: By Week / By Day menu to change the view. Actual hours will always show by week.
  • Hover over any week to see its values.

↑ Back to top


Hours/Workers (Max)/Workers (Avg)

  • Use Hours, Workers (Max), or Workers (Avg) to change how the forecast is shown on the graph and in the edit forecast grid.
  • Workers (Max) shows the highest daily crew in each week. Workers (Avg) shows the average daily crew across the week.

↑ Back to top


Edit Forecast

  • Click Edit Forecast to open the forecast grid on the page. The grid and both graphs share one timeline, so each day or week you edit lines up with the same time frame on the graphs.
  • Click a cell to edit its value.
  • Use Tab on your keyboard to move to the next cell.
  • To lock forecast values, hover over the lock row _Icon_ above Forecasted Workers and click. Job re-forecasting won’t change any week up to and including that one. Weeks you edit by hand lock automatically when you click Re-forecast.
  • Use < Today > to move along the timeline, and Zoom out to see the whole job.
  • Click Update Date to set the forecast’s last updated date to today. This resets the stale forecast flag without changing any values.

↑ Back to top


Re-forecast a Job

  1. Click Re-forecast in the Forecast Variance box, or click the Re-forecast banner in Edit Forecast mode. The job will automatically re-forecast to remove the forecast variance. RIVET takes the hours still needed to reach the projection or budget and spreads them across future weeks, following the shape of your existing labor curve. 
  2. Review Draft Projected Hours and Draft End Date. They populate from the job’s Projected Hours at Completion (or Current Hours Budget) and the job’s end date. Change either one to model a different plan and re-forecast again.
  3. Optional: click Max Workforce to cap the crew size. It starts at the job’s ideal planned peak.
  4. Optional: lock near-term weeks so they stay as planned (see Edit Forecast).
  5. Review the draft line on the Labor Loading Graph, plus the draft values in Planned Overmanning and Recommended Supervisors.
  6. Click Save Draft to keep working later, Publish to make it the current forecast, or Revert to discard it. Nothing is published until you choose to, so it’s safe to try different plans.

         More Information

When The Re-forecast Button Will Not Show

  • The Re-forecast button only shows on jobs that have started, meaning the job has actual hours or scheduled hours in the past.

  • If Current Forecasted Hours at Completion is within one worker week of the job’s projection (or budget), the Re-forecast button won’t be active. One worker week is the hours one worker spends on the job in a week. For example, if the job’s default schedule is 5 days a week at 8 hours a day, one worker week is 40 hours.
  • Re-forecasting requires the Update Forecast permission. Without it, Edit Forecast and Re-forecast are hidden and the page is view only.

↑ Back to top


Save Draft and Publish

  • After editing or re-forecasting, choose one:

    • Save Draft: keep your changes to finish later. Nothing changes elsewhere in RIVET.
    • Publish: make the draft the current forecast across RIVET.
    • Revert: discard the draft.
    • Cancel: leave Edit Forecast mode.
  • Large changes to the forecast (greater than 5% change in hours) will prompt you to choose whether to save the changes as a major or minor version.
  • When saving the new forecast as a major version, you are also able to set this new forecast as the baseline for the job going forward.

↑ Back to top


Jobs That Haven't Started

Jobs without a forecast

  • The Labor Loading and Labor Consumption graphs show placeholders until a forecast exists, and the forecast metrics show zero.
  • To create a forecast, click Edit Forecast, then click Forecast Builder to turn the job’s Current Hours Budget into a labor curve. You can also type values directly into the forecast grid.

Jobs with a forecast but no actual hours or schedules in the past

  • Click Edit Forecast to see two tools above the forecast grid:
    • Use Forecast Builder to rebuild the forecast from a standard labor curve or import one from a spreadsheet. The Curve Type label shows which curve the current forecast uses.
    • Use Move Forecast to shift or resize the forecast while keeping the total hours the same. Set a new Draft Start Date, Draft End Date, or both, then click Move Forecast. Changing only the start date shifts the whole forecast. Moving the dates closer together or farther apart compresses or stretches it.
  • You can also edit the forecast grid directly, then Save Draft or Publish.
  • Re-forecast isn’t available until the job has actual hours or past scheduled hours, and Slippage shows zero.

↑ Back to top


Planned Overmanning

  • Planned Overmanning shows whether the current published forecast or draft forecast puts more workers on the job than its ideal planned peak (1.6x the planned average workforce) after today. 
  • Hovering over the risk level will display the math behind the display.

↑ Back to top


Recommended Supervisors

  • Recommended Supervisors shows how many supervisors the current published forecast or draft forecast needs at its peak crew, based on the job’s supervisor ratio.
  • It shows Baseline Peak Supervisors, Current Peak Workers, and Current Peak Supervisors.
  • To edit the job’s role ratios, click the pencil icon next to the supervisor ratio.

↑ Back to top


Labor Consumption Graph

  • The Labor Consumption Graph shows the running total of hours over time: cumulative forecasted hours, cumulative actual hours, and cumulative baseline forecast hours, along with the job’s budget and projection at completion.
  • Hover over a week to see its values and compare hours used to date against the baseline forecast.
  • If actual hours aren’t tracked on the job, RIVET will fall back to using scheduled hours instead.
  • In Edit Forecast mode, the draft forecast also shows so you can compare it to the published one.
↑ Back to top

Slippage

 

  • Slippage compares Actual Hours to Date with Baseline Forecast to Date and shows the difference.
  • An up arrow means actuals are ahead of the baseline forecast: more hours have been used to date than planned. A down arrow means actuals are trailing the baseline forecast: fewer hours have been used to date than planned. Either can signal the job is using labor faster or slower than planned and drifting off its expected curve.
  • If Baseline Forecast is turned off, Slippage compares to the current published forecast instead.

↑ Back to top



Progress To Completion and Current Budget

 

  • Progress to Completion tracks hours and dates against the job’s projection. Current Budget tracks labor cost to date against the budget.
  • Click any bar to see the math behind it.

↑ Back to top


    Labor Plan Analysis Table

    • The Labor Plan Analysis table breaks down forecasted, actual, and current hours by To Date, To Completion, and Total at Completion, plus the variance from the job’s projection (or budget if there’s no projection).
    • Click any number to see more detail. Where a number is calculated, clicking it shows the equation.

    ↑ Back to top