Re-Forecast Feature

Re-forecast a job with the click of a button


💡 Note: This article contains interactive tutorials. Click on the targets to advance to the next step.

Contents

Navigation

Re-Forecast Button

Set Max Workers

Draft Projected Hours

Draft End Date

Draft Hours Remaining

Draft Forecast Variance

Forecast Lock

Revert/Save Draft/Publish

 

Related Material

Schedule To Your Forecast

Labor Planning Homepage

 


Navigation

  • Navigate to the Labor Planning Homepage of a job
  • The Re-forecast button will be on the Labor Planning Homepage

Re-Forecast Button

 

  • Click Re-forecast on the Labor Planning Homepage to access the Re-forecast menu above the graph below.
  • Edit the fields to make changes
  • Publish or save your new draft forecast

Set Max Workers

 

  • Manipulating the maximum number of workers allowed on the job site in the future will alter the way the job is re-forecasted
  • Lowering the number of max workers would likely cause the peak labor to be elongated
  • Increasing the number of max workers on the job may cause the span of peak labor to be shortened

Draft Projected Hours

 

  • The Draft Projected Hours relates to this specific draft of the forecast
  • The Projected Hours At Completion is the correlated field in the Job Setup section
  • RIVET will prompt the user if they wish to also update the Projected Hours at Completion with this new number entered into the draft forecast

Draft End Date

 

  • The Draft End Date is in reference to this draft forecast only
  • The corresponding field in the Job Setup section is Target End Date
  • RIVET will prompt the user to also update the jobs Target End Date with this new information entered in the draft forecast

Draft Hours Remaining

 

  • Draft Hours Remaining is the difference between the Draft Projected Hours at Completion and the Actual Hours To Date
  • Clicking this number will surface the math equation involved in the number displayed

Draft Forecast Variance

 

  • The Draft Forecast Variance is the difference between the Draft Forecasted Hours at Completion and the Projected Hours at Completion fields.
  • This number is displayed as a percent 
  • Clicking the number will display the math equation involved in this percentage

Forecast Lock

 

  • The user is able to lock a consecutive sequence of weeks that the re-forecasting feature will not touch
  • Hovering over each cell in the forecast will display the lock icon
  • Clicking the lock icon above a week will enable to weekly lock feature for that week
  • Manually edited cells will automatically receive the lock icon and the re-forecast feature will not overwrite manual changes

 

Revert/Save Draft/Publish

 

  • Revert - Discard the changes and revert to the most recently published forecast
  • Save Draft - Save the changes made and close the re-forecast menu
  • Publish - Publish the changes made to the forecast and push the data out to the rest of the application